Burying a portion of a controversial proposed power line along the Beltline more than doubles the cost of the project, American Transmission Co. said today.
ATC said its yearlong analysis of burying portions of its proposed Rockdale-West Middleton line determined that underground construction adds between $9 million and $15 million per mile to the cost compared with overhead lines.