After months of delays due to the termination of the original contractor, the demolition of the University of Wisconsinâ??s Ogg Hall should see completion by mid-November.
The demolition was originally scheduled for completion by the end of March. But after a series of mishaps including a fire and a piece of the building falling on a workerâ??s car, Dore and Associates of Bay City, Mich., was terminated by the stateâ??s Department of Administration in mid-March.